Dr. Cassiel Ato Forson, the Minister of Finance, has announced that the government has allocated US$1.7 billion into a specific account designated for the construction of the Accra-Kumasi Expressway, indicating that preparations are well underway for this flagship infrastructure initiative.
During the presentation of the 2026 Mid-Year Budget Review in Parliament on Thursday, July 23, Dr. Forson stated that these funds have been securely set aside at the Bank of Ghana and will only be utilized once the primary construction contract is awarded.
“As of July 22, 2026, US$1.7 billion has been deposited into the dedicated Accra-Kumasi Expressway Account at the Bank of Ghana. These funds are ring-fenced and will be accessed only after the main construction contract is finalized,” he informed Parliament.
The Finance Minister emphasized that this project, part of the government’s Big Push Programme, is anticipated to significantly enhance road connectivity between Ghana’s two largest commercial hubs.
The 176-kilometre, six-lane, bidirectional expressway is projected to cut travel time between Accra and Kumasi to approximately two hours, while also improving road safety, alleviating congestion, and reducing transportation costs.
Additionally, the project will feature modern interchanges, bridges, intelligent transport systems, electronic tolling, emergency response facilities, and rest areas, as detailed by Dr. Forson.
He noted that the government has made substantial strides in preparing for construction, with the Ghana Armed Forces having cleared 122 kilometres of the 120-metre-wide Right-of-Way as of July 22, 2026.
This clearance accounts for about 70 percent of the necessary corridor, with the entire route expected to be fully cleared by the first week of September 2026.
Dr. Forson mentioned that compensation assessments, environmental studies, engineering designs, and feasibility works are all progressing concurrently, with the completion of feasibility studies and detailed engineering anticipated by the end of August.
“Procurement for the main construction contract” is set to begin in September 2026, he added.
The Finance Minister expressed the government’s assurance that all necessary requirements would be fulfilled before President John Dramani Mahama officially inaugurates the construction work.
The Accra-Kumasi Expressway plays a crucial role in Ghana’s infrastructure development plan and is anticipated to enhance trade connections, minimize travel delays, and boost economic activities along one of the nation’s most heavily trafficked transport routes.